Datacenter Economics

Build the facility, fill it with silicon, serve the model. See the fully-loaded $/GPU-hr — and the real cost per million tokens — next to what renting would charge you.

Model served
Accelerator

NVIDIA · ~$48,000/chip · ~1.2 kW each

Build region

The dollar premium — power, land, labor, and the queue for capacity · ~$12M per MW to build

GPU fleet
Power · $/kWh
Blended price · $/M tok
Facility IT capacity — 50 MW
PUE — 1.25
Utilization — 50%
Total buildout$2.26B$600.0M facility + $1.66B silicon
Own vs rent · $/GPU-hr$1.89 vs $5.0062% cheaper to build
Cost per 1M tok$0.24selling at $0.25/1M blended
Breaks even at 48%$1,640,092profit / month at 50% util

Where the money goes — 50 MW facility, 30,000× B300 in United States

Line itemCapex$/month
Facility (shell, power, cooling) · 50 MW$600.0M$3,333,333 dep.
IT — 30,000× B300 + network/storage$1.66B$27,600,000 dep.
Power — 41 MW IT × PUE 1.25 × $0.08/kWh—$3,022,200
Ops & maintenance — ~4% of capex/yr—$7,520,000
Total monthly cost$2.26B$41,475,533

Facility life 15y, silicon 5y. Facility capex ~$6–14M per MW of IT depending on region; power, chip prices, and throughput are illustrative ballparks — before land premium, tax abatements, financing, and staffing detail.